Milton Union School District Site Work
BCI was contracted to perform the early site package for the new Milton Union K-12 School. The project involved 3500’ of storm line, 4000’ of waterline, and 2600’ of sewer line. During the utility installation, there was approximately 1220 cy of rock excavation. In addition to the utility work, there was 20,000 cy of excavation/embankment to grade the building pad and parking lots, 8500 cy of 304’s placed for the parking lot areas, and approximately 2000’ of road widening to add a center turn lane in front of the school.